Each season has its pros and cons. While installation is easier in summer, winter foundations often produce more reliable foundations, especially on wet or weak soils. Below, we'll break it down.
Advantages of winter installation
1. The soil is stable and compact. In
spring or fall, the ground "moves" due to moisture, and in winter,
the frozen layer stabilizes the soil, preventing piles from settling.
2. No mud or erosion. Equipment does
not sink, and the site remains clean—easy to work even on difficult terrain.
3. Convenient for seasonal sites. While
there is no vegetation, it is easy to access and lay markings without damaging
the lawn or landscaping.
4. Reduced lead times. In winter, there
are fewer orders, making it easier to find available crews and equipment, and
work often proceeds without downtime.
5. Reduced risk of damage to the
surface. The ground is frozen, preventing equipment ruts, which is important in
existing yards and under driveways.
Disadvantages and Risks
1. Increased load on equipment.
Hydraulics thicken, putting greater strain on gearboxes, requiring warm-up.
2. Uncomfortable conditions for
workers. Hands get cold, welding requires heating the metal—everything goes a
little slower.
3. Difficulty monitoring the level. In
severe frost, the water in the level or laser can freeze, requiring heating or
a dry alcohol tester.
4. Restrictions on concrete work. If
the grillage or slab is poured immediately, heating and antifreeze additives
will have to be used.
5. Temperature fluctuations. Sudden
thaws can cause piles to warp if the soil is saturated with moisture and has
frozen unevenly.
Ultimately,
winter pile installation is not a compromise, but a conscious decision, as long
as the technology is followed and no attempt is made to cut corners on
preparation.
Common mistakes during winter pile installation
and how to avoid them
Experience
shows that winter problems arise not from frost, but from carelessness and
haste. Mistakes made in the cold can be costly in the spring, when the thaw
begins and the ground begins to shift. Let's look at the most common mistakes
encountered in practice.
Mistake 1. Not
removing snow and ice before installation
A classic
example: installers rush, driving piles right through a snowdrift—and then
wonder why the foundation is shifting.
What
happens: the snow melts under the pile, creating a void, and the pile cap
sinks.
How to
avoid this: Before installation, clear the area down to solid ground, and the
hole should be free of snow or ice. It's better to spend 15 minutes clearing
the ground than to level the house later.
Mistake 2.
Not accounting for soil freezing
If the pile
doesn't penetrate the frozen layer completely and gets stuck halfway, the
foundation is doomed. In the spring, this layer will thaw, and the pile will be
"thrown up."
How to
avoid: Drive piles only to a dense supporting layer (at least 1.5–2 m deep).
Monitor the driving torque to determine where the pile has "seized."
Mistake 3. Working
without warming up the equipment
Hydraulics
thicken in winter, especially at -10°C and below. Without warming up, the pump
operates under tension and can strip the threads or blades of the pile.
How to
avoid: Be sure to warm up the installation before starting—at least 20–30
minutes, especially the gearbox and motor.
Mistake 4. Using low-quality piles
Cheap steel
performs poorly in cold weather—it breaks under load or cracks at the welds.
How to
avoid: Use piles made of certified steel. Check the quality of the welds and
coating before beginning installation.
Mistake 5. Not
welding the pile caps correctly
If you weld
at sub-zero temperatures without preheating, the metal becomes brittle, and the
weld will crack within a couple of months.
How to
avoid it: Weld at temperatures no lower than -10°C or use preheating and a
windshield. After welding, treat the weld with an anti-corrosion compound.
Mistake 6.
Not checking the plumb line
In freezing
temperatures, a level or laser can fog up or freeze. Installers rely on
eyeballing, but then end up with a 2-3 cm misalignment, causing the entire pile
cap to sag.
How to
avoid it: Use frost-resistant spirit levels and check the plumb line on each
pile, not every other one.
Mistake 7. Not
taking into account the tightening torque
In winter,
the tightening torque is higher than in summer. If you tighten the piles at
random, you risk either under-tightening or damaging the soil. How to avoid:
Monitor the torque with a torque wrench or according to the installation data.
For 108 mm diameter piles, 3500–4500 N*m on average.
All these
little details together can determine whether your foundation will stand for
decades without problems or whether you'll have to redo it in the spring.