Skip to main content

How to build a reliable foundation on peat

 

Which foundation options work on peat?

In practice, architects and designers have developed several approaches to solving the problem of building on peat soils.

        Complete peat excavation. If the peat is up to 1.5 meters deep, it is completely removed and replaced with a sand and gravel bed. A strip foundation is laid on this base. This is reliable, but expensive and labor-intensive—tens, even hundreds, of cubic meters of soil must be removed by specialized vehicles, and the same amount of high-quality sand must be brought in and compacted.

        Partial peat excavation. If the peat depth is 1.5-2 meters, trenches are dug to firm ground and a strip or columnar foundation is installed. Problem: excavation work in marshy areas is a battle against constantly incoming groundwater and collapsing wet walls.

        Pile foundation. If the peat is more than 2-3 meters thick, this is the only reasonable option. Piles penetrate weak layers and rest on dense soil. There are options: driven reinforced concrete, bored piles, or screw piles.

Driven piles require a heavy piling machine—it's simply impossible to drive one into a swampy area; it will get stuck within the first meter. Bored piles in peat quickly fill with water, and the borehole walls collapse under the pressure. Screw piles are the optimal solution: they are driven in like screws, require no excavation, and can reach any depth using a self-propelled mechanism.

Why screw piles for peat?

        No excavation work. The piles are screwed into the ground like screws into a board. There's no need to dig, pump out water, or reinforce the pit walls—all of which are a nightmare in marshy areas and distract the construction crew from their main work.

        Compact equipment or completely manual installation. A lightweight drilling rig or even four people with metal levers and labor is sufficient. Heavy equipment won't get stuck in peat.

        Unlimited extension for any depth. The standard pile is 3 meters. If deeper is needed, an extension is welded on and continued screwing. In practice, screw piles in peat bogs reach 6-8 meters or more, solving even the most complex geological problems.

        Frost heave protection. The blades are anchored below the frost line in dense soil. A smooth shaft prevents the soil from pushing the pile upward, as shear forces do not act on the smooth shaft.

        Work can be carried out at any time of year. In winter, the work can be even easier—the frozen crust facilitates movement around the site and reduces equipment sinking.

        Quick installation. A screw pile foundation is installed several times faster than a strip foundation, reducing construction time and cost.

Preliminary Work and Design

Site Geology – the Foundation of the Solution

First and foremost, geotechnical surveys with test drilling are required. This reveals the thickness of the peat layer, the type and density of the supporting soil, the groundwater level, and the chemical aggressiveness of the environment. Without this data, installation is a gamble.

The geotechnical survey process includes drilling boreholes at various points on the site (at least 3-5 points for a house), collecting soil samples from different depths, laboratory analysis of the samples, and compiling a geological cross-section. Based on this, the designer obtains an accurate picture of the soil distribution.

Calculation of Loads and Pile Parameters

The engineer determines the total building load (the weight of walls, floors, roof, snow, and wind), the estimated load-bearing capacity of a single pile in dense soil, the required number of piles, and the optimal arrangement of the piles. In peat, the pile's load-bearing capacity depends almost entirely on the blade's performance in dense soil; lateral friction along the shaft in soft peat is not taken into account.

Choosing the Diameter and Type of Pile

For a residential building on peat, the minimum shaft diameter is 89 mm, while the optimal diameter is 108 mm. Blades should be wide—the blade diameter should be 1.5 times or more greater than the shaft diameter. This design ensures good penetration into dense soil and prevents the pile from sinking.

Drainage and Site Preparation Before Piling

On peaty and waterlogged soils, site drainage is a key step. Even if piles can guarantee a secure foundation, high groundwater levels and seasonal waterlogging will create difficulties for the operation of the building and basements, as well as for installing utilities.

Important Considerations:

        If natural water flow is weak, a ring or wall drainage system is installed around the future building—a system of perforated pipes located just below the base of the future grillage or basement floor.

        For small areas, a drainage layer of sand or a mixture of sand and crushed stone within the building footprint may be sufficient; it allows water to pass through and reduces waterlogging of the upper part of the foundation.

        All drainage systems are routed to a well or drainage ditch to ensure uninterrupted drainage even after heavy rainfall or snowmelt.

Why do this:

        The water level in the ground not only affects the corrosion of the pile metal but also the long-term stability of adjacent structures and garden paths.

        Modern projects often combine peat pile foundations with artificial embankments, geotextiles, and groundwater level reduction systems—these measures improve living comfort on problematic soils.

        Drainage not only benefits the foundation but also prevents waterlogging and erosion on the site, extending the life of lawns, pavements, and drainage pumps.

The process of installing screw piles

Marking and pits

On the site, the axes of the future building are marked out using surveying instruments. Pits 20-30 cm deep are dug at the pile installation locations to facilitate initial pile positioning.

Screwing into soft soil

The pile is installed vertically in the pit and screwing begins. On soft peat, the first 1-2 meters sink easily—almost under their own weight. It is critically important at this stage to check the verticality with a level. The deviation should not exceed 2 degrees, otherwise the pile will not perform properly and the load will be unevenly distributed.

Reaching dense soil

As the pile depth increases, the torsional resistance increases. When the blades reach dense soil (sand, loam, clay), the torque increases sharply. This is the moment when the break in the pile's performance becomes noticeable. An experienced installer can sense this transition by the pile's behavior, the change in the sound of the work, and the effort of the workers. Extension and Deepening

If the standard 3-meter length is insufficient, an extension is performed. A process coupling (a larger-diameter pipe) is attached to the top end of the pile, an extension (usually 2 meters long) is welded to it, all welds are cleaned and treated with an anti-corrosion compound. Then, the drive continues with the new extension.

When working in peat, fire safety regulations must be observed—organic material is easily ignited by welding sparks.

Determining the completion of the drive

The main indicator is a sharp increase in torque. When four workers with 3-meter levers cannot drive the pile further, this means the blades are securely anchored in the dense soil.

Concreting the Cavity

After installation, all piles are cut to a uniform level. The cavities are filled with a cement-sand mixture (in a 1:3 ratio) or a ready-mixed dry concrete mix. This is critically important:

        protects the inner surface from corrosion

        prevents condensation accumulation and freezing of water

        increases the rigidity of the structure by 25-30%

        prevents pipe rupture due to frost heaving

Without concrete in winter, the water inside will freeze, expand with tremendous force, and rupture the pipe. This is a common cause of pile failure in marshy areas.

Comments

Popular posts from this blog

How to screw in helical piles?

  A helical pile (screw anchor) is a pipe with a pointed end and a spiral blade that can be screwed into the ground, similar to screwing a screw into wood. While this may seem simple, this type of work is very difficult and demanding. Screwing Methods Pile foundation elements can be screwed into the ground in two ways: ·        Using construction equipment. For this purpose, special excavator-mounted or self-propelled drilling rigs are used, which drive anchors even into frozen ground as if they were butter. This technique is also used to test the load-bearing capacity of pile structures. ·         Manual Method. This technology is used when it is impossible to bring equipment to the site. Manually installing helical anchors is very difficult and labor-intensive. Online and in print publications, this type of work is sometimes portrayed as simple and quick, but in reality, this is far from the case. Self-tappi...

Installation Considerations for Piles on Alluvial Land

  Piling on alluvial land requires a special approach. Alluvial soil typically consists of water-saturated sand with a very loose structure, obtained by hydraulic flushing from quarries or dredging. Specifics of Working with Alluvial Soil Alluvial soil differs from conventional backfill in the way it is formed. With hydraulic filling, sand is added with a large amount of water, settles in a designated area, and gradually dehydrates. This type of soil has certain characteristics. Characteristics of alluvial soil: •         High initial moisture content (30–40% or more) •         Very loose structure—porosity coefficient of 0.7–0.9 •         Unevenness across the surface—in some areas, more large particles have settled, while in others, more small ones have settled. •         Continued shrinkage under its own weight for 1–3 years. ...

Common mistakes when working with backfill

Experience shows that most foundation problems on fill soils arise from common mistakes that can be easily avoided with the right approach. Common mistakes developers make •         Forgoing engineering surveys to save money is the most common and costly mistake. Without soil data, it's impossible to accurately calculate pile length and their bearing capacity. •         Using short piles that don't reach dense soil is the second most common mistake. Developers choose standard 2.5-3 meter piles without considering the thickness of the backfill. As a result, the piles rest on soft soil and settle. •         Installing piles immediately after backfilling, without allowing time for settling, causes the fresh backfill to compact under the piles, causing them to settle. The minimum curing period for backfill is 3-6 months with good compaction. •      ...